Weekend 1: We constructed about 100 yards of new trail to move the trail to higher ground and out of a perennially wet area. The USFS reviewed my proposal and after the field visit approved the plan. We had 8 volunteers: 6 Saturday and 4 Sunday working on the project. – Mike
Weekend 2: CHATHAM Trails – Deer Hill bypass. About 600 or 700 feet with a lot of mucky spots and a stream crossing. Two rock steps for that, and about 20 rocks in the treadway hardening area (see first photo). This was on the second weekend, June 1& 2 at Cold River Camp. – Ray J.